The challenge
The Store House, Leeds, is the former House of Fraser store, which will be redeveloped into a Purpose Built Student Accommodation (PBSA) scheme.
The Challenge:
The turning point
Our solution
- The Grade 3 basement between the existing buildings desperately needed a design and products that would work with the existing building and basement.
- Grade 3 is a scenario where no seepage is acceptable. Damp areas as a result of internal air moisture/condensation are tolerable; measures might be required to manage water vapour/condensation.
The Solution:
The impact
The result
- Premcrete’s CSSW design team were able to support the customer at early stages of the design, and have the suitable products to fulfil this. Utilising years of technical knowledge and in-depth product knowledge from our manufacturing site in Hampshire, UK.
- Premcrete’s Maxiprufe Plus and Hydrocrete were utilised for effective and efficient waterproofing solutions for this project.
Location:
Leeds
Year:
2024
Main Contractor:
HG Construction
Architect:
Corstophine & Wright Architects
Structural Engineer:
Civic Engineers
Products used:
Maxiprufe Plus, Hydrocrete Admixture